City of Santa Clara logo

Legislative Public Meetings

File #: 21-1441    Version: 1 Name:
Type: Consent Calendar Status: Agenda Ready
File created: 10/3/2021 In control: Council and Authorities Concurrent Meeting
On agenda: 10/19/2021 Final action: 10/19/2021
Title: Report from the Stadium Authority Regarding Stadium Manager's Request to Execute Agreement with R.E. Cuddie Co. for Non-Slip Floor Matting CapEx Project and Related Budget Amendment
REPORT TO STADIUM AUTHORITY BOARD
SUBJECT
Title
Report from the Stadium Authority Regarding Stadium Manager's Request to Execute Agreement with R.E. Cuddie Co. for Non-Slip Floor Matting CapEx Project and Related Budget Amendment

Report
BOARD PILLAR
Ensure Compliance with Measure J and Manage Levi's Stadium

BACKGROUND
On October 8, 2019, the Stadium Authority Board (Board) approved Ordinance No. 2005 amending Chapter 17.30 of the City Code (Stadium Authority Procurement Policy), which rescinded the delegation to the Executive Director to enter into agreements without prior Board approval. As result of Ordinance No. 2005, the Stadium Manager is also required to request Board approval before entering into agreements on behalf of the Stadium Authority. As of the effective date of the Ordinance (November 8, 2019), all Stadium Authority agreements for services, supplies, materials, and equipment require the approval of the Stadium Authority Board.

As the Stadium Manager, Forty Niners Stadium Management Company, LLC is responsible for maintaining "the Stadium in the Required Condition and operate the Stadium as a quality NFL and multi-purpose public sports, public assembly, exhibit and entertainment facility" as required by the Management Agreement between the Stadium Authority and ManCo.

The Stadium Manager is requesting approval for the following:

1. Award a one-time agreement to R.E. Cuddie Co. in the amount of $53,955 for the removal and disposal of existing resilient athletic flooring from service tunnels, and the furnishing and installation of rubber resilient athletic flooring at Levi's Stadium. This work is included in the Stadium Authority FY 2021/22 CapEx budget under the Non-Slip Floor Matting line item. This was a carryover project from the FY 2019/20 CapEx Budget;

2. Authorization to execute any and all documents associated with and necessary for the award, completion, and acceptance of the project; and

3. Authorization to execute change orders ...

Click here for full text