File #: 22-1708    Version: 1 Name:
Type: Consent Calendar Status: Agenda Ready
File created: 12/1/2021 In control: Council and Authorities Concurrent Meeting
On agenda: 1/11/2022 Final action: 1/11/2022
Title: Report from the Stadium Authority Regarding Stadium Manager's Request to Execute Agreement with Bartley Pump PM, LLC for Lift Station CapEx Project
REPORT TO STADIUM AUTHORITY BOARD
SUBJECT
Title
Report from the Stadium Authority Regarding Stadium Manager's Request to Execute Agreement with Bartley Pump PM, LLC for Lift Station CapEx Project

Report
BOARD PILLAR
Ensure Compliance with Measure J and Manage Levi's Stadium

BACKGROUND
On October 8, 2019, the Stadium Authority Board (Board) approved Ordinance No. 2005 amending Chapter 17.30 of the City Code (Stadium Authority Procurement Policy), which rescinded the delegation to the Executive Director to enter into agreements without prior Board approval. As result of Ordinance No. 2005, the Stadium Manager is also required to request Board approval before entering into agreements on behalf of the Stadium Authority. As of the effective date of the Ordinance (November 8, 2019), all Stadium Authority agreements for services, supplies, materials, and equipment require the approval of the Stadium Authority Board.

As the Stadium Manager, Forty Niners Stadium Management Company, LLC is responsible for maintaining "the Stadium in the Required Condition and operate the Stadium as a quality NFL and multi-purpose public sports, public assembly, exhibit and entertainment facility" as required by the Management Agreement between the Stadium Authority and ManCo.

The Stadium Manager is requesting approval for the following:

1. Award a one-time agreement to Bartley Pump PM, LLC in the amount of $188,000 to replace pumps, floats, and controls at sewage ejector lift stations in Quadrants A, B, C, and D on the 100 level at Levi's Stadium;
2. Authorize the Stadium Manager to execute any and all documents associated with, and necessary for the award, completion, and acceptance of this Project; and
3. Authorize the Stadium Manager to execute change orders up to approximately 10% of the contract cost, or $18,800, for a total not to exceed amount of $206,800.

DISCUSSION
Stadium Authority staff reviewed the Recommendation for Award memo, supporting procurement documents, and ag...