Title: Complete Streets Review for the Creek Trail Pavement Maintenance and Rehabilitation - Phase 1 Project (Chan)
Attachments: 1. 95% Project Plans
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo or Audio
No records to display.

REPORT TO BICYCLE AND PEDESTRIAN ADVISORY COMMITTEE

SUBJECT

Title

Complete Streets Review for the Creek Trail Pavement Maintenance and Rehabilitation - Phase 1 Project (Chan)

 

Report

BACKGROUND

The Department of Public Works (DPW) is preparing the design for the Creek Trail Pavement Maintenance and Rehabilitation - Phase 1 Project (Attachment 1). The Project plans to address pavement maintenance and rehabilitation for the San Tomas Aquino Creek Trail between SR 237 and Tasman Drive, and the paved portion of the Guadalupe River Trail between the River Oaks Bridge and Thamien Park.

 

As set forth by the City of Santa Clara Complete Streets Policy, relevant transportation projects shall be coordinated with the BPAC to gather comments and recommendations regarding Complete Streets features that should be incorporated into the project.

 

DISCUSSION

Staff is currently 95 percent in the design phase for the Project. This project is considered a relevant transportation project and requires coordination with BPAC.

 

In compliance with the Complete Streets Policy, the plans are attached for BPAC to review and provide feedback.

 

Staff

Written by: Carol Shariat, Principal Transportation Planner, Public Works

Reviewed by: Steve Chan, Transportation Manager, Public Works

Approved by: Michael Liw, Assistant Director/City Engineer, Public Works

 

ATTACHMENT

1. 95% Project Plans