File #: 24-1249    Version: 1 Name:
Type: Consent Calendar Status: Agenda Ready
File created: 12/12/2024 In control: Development Review Hearing
On agenda: 1/8/2025 Final action:
Title: PUBLIC HEARING: Action on the Architectural Review (PLN22-00282) for the Demolition of an Existing Warehouse and the Construction of a Four Story 111,978 Square Foot Data Center Located at 1231 Comstock Street.
Attachments: 1. Zoning Vicinity Map, 2. General Plan Vicinity Map, 3. Project Data and Compliance Table, 4. Conditions of Approval, 5. Development Plans, 6. PMM Staff Presentation, 7. PMM Applicant Presentation
REPORT TO DEVELOPMENT REVIEW HEARING
SUBJECT
Title
PUBLIC HEARING: Action on the Architectural Review (PLN22-00282) for the Demolition of an Existing Warehouse and the Construction of a Four Story 111,978 Square Foot Data Center Located at 1231 Comstock Street.

Report
File No.: PLN22-00282
Location: 1231 Comstock Street, a 1.37-acre lot located on Comstock Street, about two hundred feet from the corner of Comstock Street and Kenneth Street; APN: 224-08-120.
General Plan: Low Intensity Office / Research & Development
Zoning: Low-Intensity Office / Research & Development (LO-RD)
Applicant: Prime Data Centers
Owner: 1231 Comstock Property LLC
Request: Architectural Review - Demolition of an existing warehouse and the construction of a 111,978 square foot data center located at 1231 Comstock Street.

PROJECT DATA
The Project Data and Compliance Table is included as Attachment 2.

POINTS FOR CONSIDERATION
* The proposed project is in a Low-Intensity Office / Research & Development (LO-RD) area consisting of both one- and multi-story data centers with some industrial development to the south of the parcel. See Zoning and General Plan Vicinity Maps in Attachments 1 and 2.
* The site currently has a single-story warehouse (built circa 1975) that will be removed to incorporate the new data center.
* Per the Santa Clara City Code (SCCC) 18.120.020 (4) and (7), the request requires Architectural Review approval through Development Review Hearing.
* Per the SCCC Table 2-13, Data Centers also require approval of a Conditional Use Permit (CUP) within the LO-RD district. The project received approval of a CUP upon appeal to the City Council on December 3, 2024.
o The project also received Variance approvals for exceeding the height limit and a reduction to required parking.
* The project proposes a 111,978 square foot data center, back-up power diesel generators located on the ground floor with offices and equipment room on the second, third and fourth floor.