Title: Action to Authorize the Use of City Electric Forces for Public Works at 2400 Condensa Street
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo or Audio
No records to display.

REPORT TO COUNCIL

SUBJECT

Title

Action to Authorize the Use of City Electric Forces for Public Works at 2400 Condensa Street

 

Report

COUNCIL PILLAR

Deliver and Enhance High Quality Efficient Services and Infrastructure

 

BACKGROUND

Section 1310 of the Santa Clara City Charter (Contracts on Public Works) states “that every contract involving an expenditure of more than one thousand dollars ($1,000) for the construction or improvement (excluding maintenance and repair) of public buildings, works, streets, drains, sewers, utilities, parks and playgrounds shall be let to the lowest responsible bidder.”  The section further states that “the City Council may declare and determine that, in its opinion, the work in question may be performed better or more economically by the City with its own employees, and after the adoption of a resolution to this effect by at least four affirmative votes, it may proceed to have said work done in the manner stated, without further observance of the provisions of this section.”

 

DISCUSSION

Staff believes that the work described below is better performed with City forces based upon the following factors: (1) the work is limited in size and scope; (2) City forces have knowledge and training in operating and maintaining the electric system that can be leveraged to more economically perform this work; and (3) bidding out the work and contracting with a private entity would not likely result in a lower overall cost or time savings.  Therefore, the staff recommends that the City Council declares and determines that City forces can better perform the installation of the following electric facilities and approve the use of City forces.

 

Estimate Number:                     40544

Location:                     2400 Condensa Street

Type of Service:                     New Business (2005)

Description of Work:                     Remove ± 165' high voltage underground conductor, ± 310' high voltage overhead conductor, 1-45' wood pole and equipment, and 1-12kv service meter.

Estimated Cost:                     $10,434

Appropriation:                     Electric Utility Capital Fund (591) Project 2005 - New Business Estimate Work

Source of Revenue:                     Customer/Developer Contribution

 

Historically, City staff has performed small project work like this under the use of City Forces exception and justification above.  In preparation for the implementation and roll out of the new Arcos crew management system scheduled to go live in spring/summer 2025, SVP staff will be developing a process to review this practice on a routine basis to provide further support for this approach.

 

ENVIRONMENTAL REVIEW

Staff recommends that the City Council determine that the action being considered is exempt from the California Environmental Quality Act (“CEQA”) pursuant to section 15302 (Class 2 -Replacement or Reconstruction) of Title 14 of the California Code of Regulations as the proposed work involves the replacement of electric facilities involving negligible expansion of capacity.

 

FISCAL IMPACT

The funds to support the staff time for work performed by Silicon Valley Power (SVP) and related construction materials for the work detailed in this report totaling $10,434 are included in the FY 2025/26 Adopted CIP Budget, in Project 2005 - New Business Estimate Work in the Electric Utility Capital Fund.  All of the referenced work will be performed by City SVP staff.  Some work associated with encroachment permits may be performed by the Department of Public Works (DPW).  DPW costs are recovered through payment of permit fees.

 

COORDINATION

This report has been coordinated with the Finance Department and City Attorney’s Office.

 

PUBLIC CONTACT

Public contact was made by posting the Council agenda on the City’s official-notice bulletin board outside City Hall Council Chambers.  A complete agenda packet is available on the City’s website and in the City Clerk’s Office at least 72 hours prior to a Regular Meeting and 24 hours prior to a Special Meeting.  A hard copy of any agenda report may be requested by contacting the City Clerk’s Office at (408) 615-2220, email clerk@santaclaraca.gov or at the public information desk at any City of Santa Clara public library.

 

RECOMMENDATION

Recommendation

1.                     Determine that the proposed action is exempt from CEQA pursuant to Section 15302 (Class 2 - Replacement or Reconstruction) of Title 14 of the California Code of Regulations; and

2.                     Declare and determine in accordance with Section 1310 of the City Charter that the public works with an estimated cost of $10,434, located at 2400 Condensa Street are better performed by the City with its own employees based on the information set forth in this Report to Council and authorize the performance of these public works consistent with this authorization.

 

Staff

Reviewed by: Nico Procos, Director of Silicon Valley Power

Approved by: Jovan D. Grogan, City Manager