Title: Bills and Claims for the month of March 2018 (Stadium Authority)
Attachments: 1. 2018-03 SCSA Bills and Claims.pdf

REPORT TO STADIUM AUTHORITY BOARD

SUBJECT

Title

Bills and Claims for the month of March 2018 (Stadium Authority)

 

Report

BACKGROUND

Disbursements made by the Stadium Authority are based on invoices submitted for payment.  Prior to payment, staff reviews all disbursement documents to ensure that they are in compliance with the goods or services provided.

The Bills and Claims listing represents the cash disbursements required of normal and usual operations during the period.  Budget control is set by the Stadium Authority Board through the budget adoption process.

DISCUSSION

Significant expenditures in this time period include:

                     Payment to Forty Niners SC Stadium Co. (StadCo) of $22,881,961 for the StadCo Subordinated Loan (Subloan).  This includes interest, the minimum required principal payment, and a principal prepayment due to excess revenues available and required to be paid to the Subloan per the Amended and Restated Stadium Lease Agreement.

                     Payment to Forty Niners Stadium Management Co. (ManCo) in the amount of $1,762,718 for stadium operations costs such as staffing, supplies, equipment, insurance, utilities, base management fee, and use of tenant improvements.

                     Three payments to the City of Santa Clara totaling $87,883 for reimbursement of General and Administrative (G&A) staff time (such as City Manager’s Office, City Attorney, Finance.)

                     Payments to various vendors of $81,190 for the following capital expenses that are part of the 2017-18 CapEx Plan: (1) propane tank storage, (2) signage, (3) public safety equipment, (4) fire sprinkler system, and (5) miscellaneous work.

                     Payment to Turner/Devcon JV of $52,049 for work related to warranty items at Levi’s Stadium.

                     Various payments to two separate consulting firms in the total amount of $21,600 as part of the stadium community engagement efforts.

                     Payment to Wilson Ihrig & Associates of $4,603 for acoustic monitoring services around the stadium.

 

 

 

ENVIRONMENTAL REVIEW

The action being considered does not constitute a “project” within the meaning of the California Environmental Quality Act (“CEQA”) pursuant to CEQA Guidelines section 15378(b)(4) in that it is a fiscal activity that does not involve any commitment to any specific project which may result in a potential significant impact on the environment.

 

FISCAL IMPACT

There is a $24,895,380 fiscal impact to the Stadium Authority.

 

PUBLIC CONTACT

Public contact was made by posting the Council agenda on the City’s official-notice bulletin board outside City Hall Council Chambers. A complete agenda packet is available on the City’s website and in the City Clerk’s Office at least 72 hours prior to a Regular Meeting and 24 hours prior to a Special Meeting. A hard copy of any agenda report may be requested by contacting the City Clerk’s Office at (408) 615-2220, email clerk@santaclaraca.gov <mailto:clerk@santaclaraca.gov> or at the public information desk at any City of Santa Clara public library.

 

RECOMMENDATION

Recommendation

Approve the list of Bills and Claims for March 2018.

 

Staff

Prepared by: Tyler Cook, Management Analyst
Reviewed by: Angela Kraetsch, Treasurer
Reviewed by: Walter C. Rossmann, Chief Operating Officer
Approved by: Deanna J. Santana, Executive Director

 

ATTACHMENTS  

1. 2018-03 SCSA Bills and Claims