REPORT TO COUNCIL
SUBJECT
Title
Action on a Resolution for the Use of City Electric Forces at Various Locations
Report
BACKGROUND
Charter Section 1310 titled Contracts on Public Works states, in part, "that every contract involving an expenditure of more than one thousand dollars ($1,000) for the construction or improvement (excluding maintenance and repair) of public buildings, works, streets, drains, sewers, utilities, parks and playgrounds shall be let to the lowest responsible bidder." The section further states that "the City Council may declare and determine that, in its opinion, the work in question may be performed better or more economically by the City with its own employees, and after the adoption of a resolution to this effect by at least four affirmative votes, it may proceed to have said work done in the manner stated, without further observance of the provisions of this section."
DISCUSSION
Staff believes that the work described below is best and most efficiently performed with City Forces based upon the following factors: (1) the work is limited in size and scope; (2) the in-house work force has knowledge and training in operating and maintaining the electric system that can be leveraged to more economically perform this work; and (3) bidding out the work and contracting with a private entity would not likely result in a lower overall cost or time savings. Therefore, staff recommends that the City Council make a finding that City Forces can best perform the installation of the following electric facilities and approve the use of City Forces.
Estimate Number: 35348
Location: 3800 Bassett Street
Type of Service: Load Increase
Description of Work: Replace existing 3-phase 750kVA padmounted transformer with a new 3-phase 2500kVA padmounted transformer. Replace 1200A meter main with 3000A meter main.
Estimated Cost: $46,213.77
Appropriation: Electric Utility Fund (591) Project 2005 - New Business Estimate Work
Source of Revenue: Customer/Devel...