REPORT TO STADIUM AUTHORITY BOARD
SUBJECT
Title
Action on Stadium Manager's Request to Approve an Agreement with Giant Construction LLC for the Women's Locker Room CapEx Project

Report
BOARD PILLAR
Ensure Compliance with Measure J and Manage Levi's Stadium

BACKGROUND
As the Stadium Manager of Levi's Stadium, Forty Niners Stadium Management Company LLC is responsible for maintaining "the Stadium in the Required Condition and operate the Stadium as a quality NFL and multi-purpose public sports, public assembly, exhibit and entertainment facility" as required by the Management Agreement between the Stadium Authority and Stadium Manager.

The Stadium Authority Fiscal Year (FY) 2023/24 Capital Expense (CapEx) Budget includes a $329,123 line item for a Women's Locker Room project. The project, as described, converts a portion of the auxiliary locker room area to accommodate a larger private space for female athletes, performers, officials, and other female event day sporting and entertainment professionals visiting or working events at Levi's Stadium. The project will include the design, permitting, and construction of alterations necessary to accommodate these new designated spaces necessary to provide equal accommodations. This area is not related to the Home Team Locker Room and Visitor Team Locker Room, which are located in a different area of the Stadium.

The Stadium Manager is requesting approval for the following actions related to the Women's Locker Room CapEx Project:

1. Approve a one-time agreement with Giant Construction LLC in the amount of $239,900 to renovate the auxiliary locker room areas to accommodate a larger private space for female event day professionals visiting or working events at Levi's Stadium;
2. Authorize the Stadium Manager to execute any and all documents associated with, and necessary for the award, completion, and acceptance of the project; and
3. Authorize the Stadium Manager to execute change orders up to $23,990, for a total n...