File #: 21-861    Version: 1 Name:
Type: Department Report Status: Agenda Ready
File created: 6/10/2021 In control: Council and Authorities Concurrent Meeting
On agenda: 7/13/2021 Final action: 7/13/2021
Title: Action on Additional Authorization to Execute Change Orders for the Serra Substation Construction Project Contract No. 2104 with the Newtron Group
Attachments: 1. RTC 20-647 - Action on the Award of the Public Works Contract for the Serra Substation Construction Project, 2. RTC 21-503 - Action on the Award of the Public Works Contract for the Serra Substation Construction Project, 3. Serra Substation Potential Change Orders
REPORT TO COUNCIL
SUBJECT
Title
Action on Additional Authorization to Execute Change Orders for the Serra Substation Construction Project Contract No. 2104 with the Newtron Group

Report
COUNCIL PILLAR
Deliver and Enhance High Quality Efficient Services and Infrastructure

BACKGROUND
On January 14, 2020, Council awarded the Public Works Contract (Contract No. 2104A) for the Serra Substation Construction Project (Project) to the Newtron Group for the bid price of $4,987,510 plus a 10% contingency of $498,751 for a total authorized contract amount $5,486,261. The Serra Substation Construction Project is a rebuild of the existing substation, which has obsolete equipment nearing the end of its useful service life. The rebuild will allow Silicon Valley Power (SVP) to continue to provide service to customers while improving service reliability and system redundancy. Work includes replacing the existing single 16 MVA transformer bank and switchgear with two 20 MVA transformer banks, new switchgear, and control room that meets SVP's current standards. The site is physically constrained within the current lease of the property owner. The Public Works Contract consists of all required work to reconstruct the Serra Substation at the existing location along Lawrence Expressway.

On January 12, 2021, Council authorized the City Manager to execute Change Order No. 4 to add the replacement of the existing wood transmission poles with steel self-supporting transmission poles to mitigate field conflicts with new underground structures. Change Order No. 4 increased the authorized funding amount by $715,512 and additional contingency of $375,000 for a contract total not-to-exceed amount of $6,576,773. Due to the confined construction area and associated COVID-19 work requirements, staff recommended using the Newtron Group as the prime contractor for this additional work activity. The construction phase of the Project is at 75% of completion.

DISCUSSION
The Serra Substati...