REPORT TO STADIUM AUTHORITY BOARD
SUBJECT
Title
Report from the Stadium Authority for Action Regarding Stadium Manager's Request to Award Agreement to Devcon Construction, Inc. to Remove and Replace Existing Padded Club Seats in Levi's Stadium (New Seating - Bowl Padded Seats Replacement Project - Lower and Mid Level Club Seating Bowl CapEx Project)
Report
BOARD PILLAR
Ensure Compliance with Measure J and Manage Levi's Stadium
BACKGROUND
On October 8, 2019, the Stadium Authority Board (Board) approved Ordinance No. 2005 amending Chapter 17.30 of the City Code (Stadium Authority Procurement Policy), which rescinded the delegation to the Executive Director to enter into agreements without prior Board approval. As result of Ordinance No. 2005, the Stadium Manager is also required to request Board approval before entering into agreements on behalf of the Stadium Authority. As of the effective date of the Ordinance (November 8, 2019), all Stadium Authority agreements for services, supplies, materials, and equipment require the approval of the Stadium Authority Board.
As the Stadium Manager, Forty Niners Stadium Management Company, LLC is responsible for maintaining "the Stadium in the Required Condition and operate the Stadium as a quality NFL and multi-purpose public sports, public assembly, exhibit and entertainment facility" as required by the Management Agreement between the Stadium Authority and ManCo.
The Stadium Manager is requesting approval for the following actions related to the New Seating - Bowl Padded Seats Replacement Project - Lower and Mid Level Club Seating Bowl Capital Expense (CapEx) Project:
1. Award a one-time agreement to Devcon Construction, Inc. in the amount of $3,094,392 to remove and replace the existing padded club seats in Levi's Stadium;
2. Authorize the Stadium Manager to execute any and all documents associated with, and necessary for the award, completion, and acceptance of the project; and
3. Authorize the Stadium Manager t...
Click here for full text