Legislation Details

File #: 26-675    Version: 1 Name:
Type: Consent Calendar Status: Agenda Ready
File created: 6/3/2026 In control: City Council and Authorities Concurrent
On agenda: 11/17/2026 Final action:
Title: Action on the Award of an Agreement for Services to Thermal Mechanical, Inc. for HVAC Restoration Services at the Senior Center Natatorium for a Not-To-Exceed Amount of $448,139, and Approval of Related Budget Amendment
Attachments: 1. Agreement - CSC - Thermal Mechanical - HVAC Restoration.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo or Audio
No records to display.
REPORT TO COUNCIL

SUBJECT
Title
Action on the Award of an Agreement for Services to Thermal Mechanical, Inc. for HVAC Restoration Services at the Senior Center Natatorium for a Not-To-Exceed Amount of $448,139, and Approval of Related Budget Amendment

Report
BACKGROUND
The Senior Center Natatorium’s Heating, Ventilation, and Air Conditioning (HVAC) system was installed approximately 20 years ago and experienced its first major failure in 2021. Since then, the system has experienced multiple significant failures, and its condition has continued to deteriorate, affecting overall reliability and performance. The HVAC is critical to maintaining appropriate temperature, humidity, and air quality conditions within the Natatorium, ensuring a safe and comfortable environment for patrons and staff.

Natatorium facilities operate under unique environmental conditions due to the presence of chloramines generated through pool water treatment processes. Without adequate ventilation, chloramines can accumulate within the facility, resulting in poor indoor air quality, accelerated corrosion of building systems and equipment, and potential health and safety concerns. As a result, natatorium HVAC equipment and replacement components must be specially designed to withstand prolonged exposure to elevated chloramine concentrations and cannot be readily substituted with standard commercial HVAC equipment.

The existing HVAC system is planned for full replacement as a part of a future, multi-phase Capital Improvement Project. The project is anticipated to begin with the design phase in approximately two years, followed by construction. Based on the current project schedule, completion of the HVAC replacement is expected within approximately five years.

To maintain safe and reliable facility operations until the replacement project is complete, staff recommends undertaking significant repairs of the existing system, including in-kind replacement of critical components. This inter...