Title: Action (1) Authorizing the City Manager to Negotiate and Execute a 20MW Power Purchase Agreement with Bloom Energy to supply power to Amazon Web Services (AWS) and a separate Offtake Agreement with AWS; and (2) Authorizing the City Manager to Negotiate and Execute up to an additional 80 MW of Power Purchase Agreements with qualified vendors for in-City generation solutions and all needed agreements with Customers.
Attachments: 1. POST MEETING MATERIAL
REPORT TO COUNCIL
SUBJECT
Title
Action (1) Authorizing the City Manager to Negotiate and Execute a 20MW Power Purchase Agreement with Bloom Energy to supply power to Amazon Web Services (AWS) and a separate Offtake Agreement with AWS; and (2) Authorizing the City Manager to Negotiate and Execute up to an additional 80 MW of Power Purchase Agreements with qualified vendors for in-City generation solutions and all needed agreements with Customers.

Report
COUNCIL PILLAR
Deliver and Enhance High Quality Efficient Services and Infrastructure

BACKGROUND
In November 2019, Silicon Valley Power (SVP) management met to discuss the strategic priorities for SVP and identified that the City would experience significant electric load growth requiring SVP to develop a capital improvement strategy to meet the City of Santa Clara's potential load growth. Staff developed both near-term and long-term strategies to accommodate approved growth and develop the necessary infrastructure plan options.

On October 13, 2020, the City Council authorized the City Manager to execute master service agreements with several engineering consultant firms to support SVP in system expansion (RTC # 20-854).

On April 6, 2021, staff presented a comprehensive review of upcoming load growth and capital projects to the City Council as part of the SVP Quarterly Report. The presentation concluded with the next steps, including the preparation of a system growth strategy to be presented at a future City Council meeting.

On September 28, 2021, the City Council accepted SVP's Three-Year System Growth Plan Strategy (RTC # 21-871). This plan identified $300 million in proposed projects for both near-term and long-term capital improvement projects needed to support anticipated system growth and to replace end-of life equipment for system reliability.

On April 5, 2022, the City Council adopted Resolution # 22-9069 adding new and updated connection and load development fees for SVP (RTC # 22-449). Addition...

Click here for full text