File #: 20-878    Version: 1 Name:
Type: Consent Calendar Status: Agenda Ready
File created: 9/10/2020 In control: Council and Authorities Concurrent Meeting
On agenda: 10/27/2020 Final action: 10/27/2020
Title: Action on Amendment No. 1 to the Agreement with YEI Engineers, Inc. for Citywide Emergency Generator Replacement - Phase 1 Project
Attachments: 1. Original Agreement, 2. Amendment No. 1

REPORT TO COUNCIL

SUBJECT

Title

Action on Amendment No. 1 to the Agreement with YEI Engineers, Inc. for Citywide Emergency Generator Replacement - Phase 1 Project

 

Report

 

COUNCIL PILLAR

Deliver and Enhance High Quality Efficient Services and Infrastructure

 

BACKGROUND

On October 2, 2017, Council approved an agreement with YEI Engineers, Inc. (YEI) to provide engineering services for Citywide Emergency Generator Replacement - Phase 1 (Project) for public works bidding (Attachment 1). The agreement expires on December 31, 2020.

 

On August 18, 2020, Council awarded the Construction Contract for the Project to the lowest responsible and responsive bidder, Rosendin Electric, Inc.

 

DISCUSSION

The remaining tasks for YEI include providing support services during the Construction and Post-Construction Phases of the Project which is estimated to be completed in late 2021. The Project’s estimated construction completion date is December 2021, however this timeframe is subject to change based on the current issues related to the COVID-19 pandemic. Since the agreement expires in the next few months and construction will not be completed, an amendment to extend the term is needed.

 

The proposed Amendment No. 1 attached to this report (Attachment 2) extends the contract time to the completion of work described in Exhibit A - Scope of Services of the Agreement. Staff recommends approval of Amendment No. 1 to the Agreement for YEI so the remaining tasks in the Agreement can be completed.

 

ENVIRONMENTAL REVIEW

The action being considered does not constitute a “project” within the meaning of the California Environmental Quality Act (“CEQA”) pursuant to CEQA Guidelines section 15378(a) as it has no potential for resulting in either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment.

 

FISCAL IMPACT

There is no fiscal impact as the proposed amendment does not change the total compensation. The fees for the remaining tasks are already encumbered in the original Agreement.

 

COORDINATION

This report has been coordinated with Finance Department and City Attorney’s Office.

 

PUBLIC CONTACT

Public contact was made by posting the Council agenda on the City’s official-notice bulletin board outside City Hall Council Chambers. A complete agenda packet is available on the City’s website and in the City Clerk’s Office at least 72 hours prior to a Regular Meeting and 24 hours prior to a Special Meeting. A hard copy of any agenda report may be requested by contacting the City Clerk’s Office at (408) 615-2220 or email clerk@santaclaraca.gov <mailto:clerk@santaclaraca.gov>.

 

RECOMMENDATION

Recommendation

Approve and authorize the City Manager to execute Amendment No. 1 to the Agreement with YEI Engineers, Inc. for Citywide Emergency Generator Replacement - Phase 1 Project.

 

Staff

Reviewed by: Craig Mobeck, Director of Public Works

Approved by: Deanna J. Santana, City Manager

ATTACHMENTS