City of Santa Clara logo

Legislative Public Meetings

File #: 22-735    Version: 1 Name:
Type: Public Hearing/General Business Status: Agenda Ready
File created: 5/18/2022 In control: Council and Authorities Concurrent Meeting
On agenda: 7/12/2022 Final action:
Title: Public Hearing: Action on a Resolution of Necessity to Acquire Certain Real Property Interests on 1040 Di Giulio Avenue, Santa Clara, California, from John P. Anderson, as Trustee of the John P. Anderson Revocable Living Trust, Dated September 11, 1984
Attachments: 1. December 14, 2021, Offer Letter, 2. Resolution of Necessity, 3. Resolution No. 22-9125, 4. POST MEETING MATERIAL
REPORT TO COUNCIL
SUBJECT
Title
Public Hearing: Action on a Resolution of Necessity to Acquire Certain Real Property Interests on 1040 Di Giulio Avenue, Santa Clara, California, from John P. Anderson, as Trustee of the John P. Anderson Revocable Living Trust, Dated September 11, 1984

Report
COUNCIL PILLAR
Deliver and Enhance High Quality Efficient Services and Infrastructure

BACKGROUND
The City of Santa Clara's Electric Utility, Silicon Valley Power (SVP), is proposing to construct approximately 0.6 miles of new single circuit 60 kilovolt (kV) overhead transmission line within the eastern area of the City of Santa Clara. One of the objectives of the Memorex Junction Transmission Line Extension Project ("Project") is to provide service to the new Memorex Junction Substation to be constructed as a part of the 1200 Memorex Development and potential other datacenter or industrial developments within the vicinity.

Upon completion, the transmission line will provide service to the Memorex Junction Substation which is to be constructed as a part of the 1200 Memorex Development. Four other potential developments have expressed interest in the area and would be eligible to connect to the new transmission line. Future 60kV service connections to this facility will be evaluated in accordance with Silicon Valley Power's Rules and Regulations, SVP Standard Document SD 5040, standard comments produced by SVP during Project Clearance Committee reviews, City Code, and Specific Development agreements.

The new 60kV transmission line would be constructed along or crossing the following city streets: Lafayette Street, Shulman Avenue, Memorex Drive, Ronald Street and Di Giulio Avenue.

The City Council has previously taken a number of actions on the Project:

* April 14, 2021 - Approved a Funding Agreement with 1220 Santa Clara PropCo, LLC, Relating to City Predesign Engineering Activities for the Memorex Junction Substation Project and Related Budget Amendment
* November ...

Click here for full text