File #: 21-1409    Version: 1 Name:
Type: Consent Calendar Status: Passed
File created: 12/17/2020 In control: Council and Authorities Concurrent Meeting
On agenda: 2/9/2021 Final action: 2/9/2021
Title: Action on a Resolution Approving Purchase and Sale Agreements for Electric Utility Easements on the South Loop Reconfigure Project; 2755 Lafayette Street and 630 Martin Avenue
Attachments: 1. Resolution, 2. Agreement for Purchase and Sale - 2755 Lafayette Street [224-04-06], 3. Agreement for Purchase and Sale - 630 Martin Avenue [224-35-014], 4. Resolution No. 21-8937
REPORT TO COUNCIL
SUBJECT
Title
Action on a Resolution Approving Purchase and Sale Agreements for Electric Utility Easements on the South Loop Reconfigure Project; 2755 Lafayette Street and 630 Martin Avenue

Report
COUNCIL PILLAR
Deliver and Enhance High Quality Efficient Services and Infrastructure

BACKGROUND
The City of Santa Clara's Electric Utility, Silicon Valley Power (SVP), is proposing to construct approximately 3.5 miles of new single and double circuit 60 kilovolt (kV) overhead transmission lines within the northeastern area of the City. SVP's primary objective of the South Loop Reconfigure Project (Project) is to shift the electrical load demand that is currently being seen on the South Loop Circuit to the East Loop Circuit to increase capacity and system reliability.

The City Council has previously taken a number of actions on this Project:
* June 16, 2015 - Adopted the FY 2015/16 Capital Improvement Program (CIP) Budget which included the initial funding for the engineering for this 60kV conductoring and upgrading project.
* July 12, 2016 - Approved a professional services agreement with Electrical Consultants, Inc. to provide transmission line engineering design services which included reconfiguring the south transmission loop.
* January 14, 2020 - Amended a service agreement with Valbridge Property Advisors to perform appraisal services as part of the easement acquisition for the Project.
* July 7, 2020 - Adopted the Negative Declaration and Mitigation, Monitoring and Reporting Program for the Project and increased the capital funding of the Transmission System Reinforcements Capital Improvement Program Project (No. 2124) by $6,300,000.
* October 13, 2020 - Approved three Purchase and Sale Agreements for Electric Utility Easements
* November 10, 2020 - Approved two Purchase and Sale Agreements for Electric Utility Easements
* November 17, 2020 - Approved four Purchase and Sale Agreements for Electric Utility Easements
* December 16, 2020 - A...